Law Firm - Datacenter Refresh and UPS Upgrade
Tuesday 1 May 2012
Provision of project management and engineering for a Tokyo data center, upgrading APC Symmetra to the latest Symmetra LX. Additionally, we took advantage of the opportunity to be allowed by the busy legal professionals to have a full 40-hour time window, to bolster the data center's earthquake proofing, and to remove old equipment and cable, as well as to re-vamp the structured cabling in the racks to gain more space for growth. This project long to plan, and a challenge to execute, given the many teams involved - project, construction, electricity, cabling and test.
Team Members - PM x 2, Consultant x 2, Engineer x 10, Construction-related x 20, Key User x 2.
Users -40
Project Duration (Months) -36 person-months
Project Effort (Months)-400 person-months
Sites -Tokyo, NY
Problems -
- End of life UPS equipment
- Earthquake resistance could be improved
- General datacenter "entropy" such as old cable, old equipment
- No space in racks
- Labeling could be improved
Solution -
- Implement latest redundant APC Symmetra LX 8Kva with 2-hour runtime
- Bolster earthquake proofing, which necessitates removal of all equipment and racks, and reinstallation of the entire DC.
- Remove old equipment and cable, and rearrange to make space
- Label so that things are easy to find and troubleshoot
Benefits -
- Greatly improved fireproofing and earthquake resistance in DC.
- Space created inside and around racks, removing the need for space for additional new racks.
- Cleanup included numbered patch cables, to allow traceabilty for better troubleshooting.
- Latest APC UPS technology now in place, for a supported and robust solution.
Technology -
- APC Symmetra LX 8KVa UPS
- APC System Racks